Following Planning Permission Complications the new Cambridge North Station now has a Completion Date at Last
Planning permission for the new Cambridge North Station, which is expected to handle 3,000 passengers a day in the north east of the city, was originally granted in 2013. However, when Cambridgeshire County Council, the original promoters of the new station, had to hand the project over to Network Rail, it was decided that a second planning application would have to made and the whole process repeated. Thie time taken to do this then led to the project being delayed further since it became entangled in various financial reviews. Altogether these administrative obstacles pushed the completion back by nearly three years